- Visions18
- Visions17
- Visions16
- Visions15
- Visions14
-
Construction
- Node Installations Complete!
- Six on the Seafloor!
- New Segment 7
- Defining the SIA
- PN5A Successfully Deployed!
- PN 5A – Jointing Operations
- PN 5A Installation Continues
- On Site to Install PN5A
- Transit to Node 5A
- Port Call in Portland
- PN1D is Installed!
- Burial and Inspection Completed ...
- Humpbacks Visit
- Cable Burial Node PN1C
- Milestone: PN1C is Installed
- Photos of Final Inspection of P ...
- Another RSN Node is Born!
- Cable Burial Continues at Secon ...
- Second Node Installed!
- Splicing Node PN1B into Segment ...
- Recovering End of Segment 3
- Word for the Day: Persistence
- Major Milestone: First Node Ins ...
- Primary Node 1A Powered Up on D ...
- Recovering and Testing Cable Se ...
- OOI Primary Node Installation B ...
- Cable Installation Update
- Dolphins and Puffins and Molas, ...
- Day 51: Seabed Cable Lay Comple ...
- Dynamic Positioning
- Update on Cable Installation
- Completion of Segment 1 Burial
- Leaps and Bounds at the Shore S ...
- Segment 5 Installation Complete ...
- Laying Segment 5
- Bustling Shore Station
- At-Sea Installation Phases
- Installing the Land Cable
- TE SubCom Dependable Propulsion ...
- Divers at Work
- The Day After
- Second OOI Cable Landed
- Second Cable Landing Reschedule ...
- OOI Open House in Pacific City, ...
- The Cable has Landed!
- Last Grapnel Run Before Landing ...
- Preparing for the Cable Landing ...
- Seaplow 101
- Marine Mammal Observations
- Communicating with a Fishing Ve ...
- Cable Deployment Update
- Off Pacific City, Oregon
- Finished with First Segment
- Deploying Repeaters
- Start of First Cable Segment
- Leaving Astoria
- Meeting the Cable Ship in Astor ...
- Cable Laying Vessel Underway
- Photos of OOI Cable Loading
- Northern conduit installed
- Northern Conduit drilling compl ...
- Bubble test for the Southern Co ...
- Drilling of the Northern Condui ...
- Update on Drilling
July 2013
May 2013
December 2012
October 2012
August 2012
July 2012
April 2012
March 2012
January 2012
October 2011
September 2011
August 2011
July 2011
June 2011
March 2011
February 2011
October 2010
June 2010
May 2010
April 2010
- Visions13
- Visions12
- Visions11
- Enlighten
Related Blogs
990 km of Cable Route Surveyed
Monday, April 19, 2010
From Cecile Durand on RSN cable route survey cruise
All of our deep-water surveys from Axial seamount to the base of Oregon’s continental slope are now complete. This totals about 990km of cable route so far.
We have also managed to do most of the survey work in the approach to Pacific City and should soon be heading south towards the Newport Line survey (Segments 2 through 4).
The bad weather encountered at the beginning of our survey operations was followed by really nice conditions close to shore… good timing! Thanks to good weather, we’ve been able to work more or less non-stop (24 hrs a day), with a few interruptions due to equipment issues.
So far, with some route development, we have been able to skirt around areas of hard bottom where cable burial would be a challenge. Our goal is to achieve 100% burial from the shore to a position just past the 700 fathoms mark offshore (~1300m) in order to reduce the risk of cable damage due to fishing activities. Our contractor (L3- Maripro) with the support of the TE Subcom (formerly TYCO) onboard rep is now engineering the post-survey route for all segments that have been successfully surveyed. We’re making progress, ensuring that no data gaps are left behind and sufficient data are collected before we leave this region.