- Visions18
- Visions17
- Visions16
- Visions15
- Visions14
-
Construction
- Node Installations Complete!
- Six on the Seafloor!
- New Segment 7
- Defining the SIA
- PN5A Successfully Deployed!
- PN 5A – Jointing Operations
- PN 5A Installation Continues
- On Site to Install PN5A
- Transit to Node 5A
- Port Call in Portland
- PN1D is Installed!
- Burial and Inspection Completed ...
- Humpbacks Visit
- Cable Burial Node PN1C
- Milestone: PN1C is Installed
- Photos of Final Inspection of P ...
- Another RSN Node is Born!
- Cable Burial Continues at Secon ...
- Second Node Installed!
- Splicing Node PN1B into Segment ...
- Recovering End of Segment 3
- Word for the Day: Persistence
- Major Milestone: First Node Ins ...
- Primary Node 1A Powered Up on D ...
- Recovering and Testing Cable Se ...
- OOI Primary Node Installation B ...
- Cable Installation Update
- Dolphins and Puffins and Molas, ...
- Day 51: Seabed Cable Lay Comple ...
- Dynamic Positioning
- Update on Cable Installation
- Completion of Segment 1 Burial
- Leaps and Bounds at the Shore S ...
- Segment 5 Installation Complete ...
- Laying Segment 5
- Bustling Shore Station
- At-Sea Installation Phases
- Installing the Land Cable
- TE SubCom Dependable Propulsion ...
- Divers at Work
- The Day After
- Second OOI Cable Landed
- Second Cable Landing Reschedule ...
- OOI Open House in Pacific City, ...
- The Cable has Landed!
- Last Grapnel Run Before Landing ...
- Preparing for the Cable Landing ...
- Seaplow 101
- Marine Mammal Observations
- Communicating with a Fishing Ve ...
- Cable Deployment Update
- Off Pacific City, Oregon
- Finished with First Segment
- Deploying Repeaters
- Start of First Cable Segment
- Leaving Astoria
- Meeting the Cable Ship in Astor ...
- Cable Laying Vessel Underway
- Photos of OOI Cable Loading
- Northern conduit installed
- Northern Conduit drilling compl ...
- Bubble test for the Southern Co ...
- Drilling of the Northern Condui ...
- Update on Drilling
July 2013
May 2013
December 2012
October 2012
August 2012
July 2012
April 2012
March 2012
January 2012
October 2011
September 2011
August 2011
July 2011
June 2011
March 2011
February 2011
October 2010
June 2010
May 2010
April 2010
- Visions13
- Visions12
- Visions11
- Enlighten
Operations are continuing to grapple and recover the cable segment ends for OOI RSN Primary Node 3A at Axial Seamount. In the meantime, Paul Hagstrom, OOI-RSN Associate Project Manager/Senior Project Engineer at the Consortium for Ocean Leadership, who is on board the TE SubCom Dependable for the duration of the RSN Primary Node Installation work, has provided a useful explanation of the Science Interface Assembly, which is installed in all the primary nodes except for PN5A.
Science Interface Assembly (SIA): The SIA in a primary node has all the active optics, communications, low-voltage power, and control circuitry. The SIA is designed to be installed into or removed from a primary node on the seafloor using a remotely operated vehicle (ROV). There is no science currently planned for the Mid-Plate Node, PN5A. However, in order to to complete all testing from the shore station while the node was still on the deck of the vessel, the spare SIA was installed in the PN5 frame, which is known as the Backbone Interface Assembly (BIA). Prior to launch on 11 August, the spare SIA was removed from the PN5A BIA. This SIA will eventually be stored onshore. If, at some future date, the RSN system is expanded from Primary Node 5A, the SIA will be configured and installed in the BIA to support that expansion.
--Nancy Penrose, OOI Communications Coordinator