- Visions18
- Visions17
- Visions16
- Visions15
- Visions14
-
Construction
- Node Installations Complete!
- Six on the Seafloor!
- New Segment 7
- Defining the SIA
- PN5A Successfully Deployed!
- PN 5A – Jointing Operations
- PN 5A Installation Continues
- On Site to Install PN5A
- Transit to Node 5A
- Port Call in Portland
- PN1D is Installed!
- Burial and Inspection Completed ...
- Humpbacks Visit
- Cable Burial Node PN1C
- Milestone: PN1C is Installed
- Photos of Final Inspection of P ...
- Another RSN Node is Born!
- Cable Burial Continues at Secon ...
- Second Node Installed!
- Splicing Node PN1B into Segment ...
- Recovering End of Segment 3
- Word for the Day: Persistence
- Major Milestone: First Node Ins ...
- Primary Node 1A Powered Up on D ...
- Recovering and Testing Cable Se ...
- OOI Primary Node Installation B ...
- Cable Installation Update
- Dolphins and Puffins and Molas, ...
- Day 51: Seabed Cable Lay Comple ...
- Dynamic Positioning
- Update on Cable Installation
- Completion of Segment 1 Burial
- Leaps and Bounds at the Shore S ...
- Segment 5 Installation Complete ...
- Laying Segment 5
- Bustling Shore Station
- At-Sea Installation Phases
- Installing the Land Cable
- TE SubCom Dependable Propulsion ...
- Divers at Work
- The Day After
- Second OOI Cable Landed
- Second Cable Landing Reschedule ...
- OOI Open House in Pacific City, ...
- The Cable has Landed!
- Last Grapnel Run Before Landing ...
- Preparing for the Cable Landing ...
- Seaplow 101
- Marine Mammal Observations
- Communicating with a Fishing Ve ...
- Cable Deployment Update
- Off Pacific City, Oregon
- Finished with First Segment
- Deploying Repeaters
- Start of First Cable Segment
- Leaving Astoria
- Meeting the Cable Ship in Astor ...
- Cable Laying Vessel Underway
- Photos of OOI Cable Loading
- Northern conduit installed
- Northern Conduit drilling compl ...
- Bubble test for the Southern Co ...
- Drilling of the Northern Condui ...
- Update on Drilling
July 2013
May 2013
December 2012
October 2012
August 2012
July 2012
April 2012
March 2012
January 2012
October 2011
September 2011
August 2011
July 2011
June 2011
March 2011
February 2011
October 2010
June 2010
May 2010
April 2010
- Visions13
- Visions12
- Visions11
- Enlighten
In preparation for OOI RSN primary node deployment in summer 2012, tests of rigging configurations took place on April 17 and 18, 2012 dockside at Swan Island in Portland, Oregon. The seven primary nodes on the RSN system are terminal points on the main, or backbone, cable, that distribute power (8 kilowatts) and bandwidth (10 Gbits/second) to the secondary infrastructure (sensors, instruments, lower-voltage nodes, full water-column moorings, and wet-mateable connectors for remotely operated vehicles).
One of the primary nodes built by L-3 Maripro, the OOI RSN prime contractor, was offloaded from a flatbed truck on the Swan Island dock and onto the fantail of the cableship TE SubCom Dependable, the commercial telecommunications cableship that will be used to install the primary nodes in July and August 2012. The C.S. Dependable is the same vessel that was involved in the installation of the Regional Scale Nodes primary cable in summer 2011.
Several different rigging configurations were tested to identify the safest and best method for deploying the node off the fantail and into the water as well as verifying all deck load positions. UW OOI ocean engineer, Skip Denny, and marine ops manager, Brian Ittig, traveled to Portland and were part of the dockside testing team, along with L-3 MariPro representatives and TE SubCom personnel.