- Visions18
- Visions17
- Visions16
- Visions15
- Visions14
-
Construction
- Node Installations Complete!
- Six on the Seafloor!
- New Segment 7
- Defining the SIA
- PN5A Successfully Deployed!
- PN 5A – Jointing Operations
- PN 5A Installation Continues
- On Site to Install PN5A
- Transit to Node 5A
- Port Call in Portland
- PN1D is Installed!
- Burial and Inspection Completed ...
- Humpbacks Visit
- Cable Burial Node PN1C
- Milestone: PN1C is Installed
- Photos of Final Inspection of P ...
- Another RSN Node is Born!
- Cable Burial Continues at Secon ...
- Second Node Installed!
- Splicing Node PN1B into Segment ...
- Recovering End of Segment 3
- Word for the Day: Persistence
- Major Milestone: First Node Ins ...
- Primary Node 1A Powered Up on D ...
- Recovering and Testing Cable Se ...
- OOI Primary Node Installation B ...
- Cable Installation Update
- Dolphins and Puffins and Molas, ...
- Day 51: Seabed Cable Lay Comple ...
- Dynamic Positioning
- Update on Cable Installation
- Completion of Segment 1 Burial
- Leaps and Bounds at the Shore S ...
- Segment 5 Installation Complete ...
- Laying Segment 5
- Bustling Shore Station
- At-Sea Installation Phases
- Installing the Land Cable
- TE SubCom Dependable Propulsion ...
- Divers at Work
- The Day After
- Second OOI Cable Landed
- Second Cable Landing Reschedule ...
- OOI Open House in Pacific City, ...
- The Cable has Landed!
- Last Grapnel Run Before Landing ...
- Preparing for the Cable Landing ...
- Seaplow 101
- Marine Mammal Observations
- Communicating with a Fishing Ve ...
- Cable Deployment Update
- Off Pacific City, Oregon
- Finished with First Segment
- Deploying Repeaters
- Start of First Cable Segment
- Leaving Astoria
- Meeting the Cable Ship in Astor ...
- Cable Laying Vessel Underway
- Photos of OOI Cable Loading
- Northern conduit installed
- Northern Conduit drilling compl ...
- Bubble test for the Southern Co ...
- Drilling of the Northern Condui ...
- Update on Drilling
July 2013
May 2013
December 2012
October 2012
August 2012
July 2012
April 2012
March 2012
January 2012
October 2011
September 2011
August 2011
July 2011
June 2011
March 2011
February 2011
October 2010
June 2010
May 2010
April 2010
- Visions13
- Visions12
- Visions11
- Enlighten
Anticipation intensifies, even as the recent flurry of activity at the OOI shore station in Pacific City has begun to subside. Installation and operational checks have been completed on all but the Line Monitoring Equipment* component of the Submarine Line Terminal Equipment**, land cables are extended from the shore station and spliced to ocean cables at the beach manhole, and fine details are being attended to as the Power Feed Equipment*** installation nears the end. We've seen significant progress amidst an assortment of challenges and gained a fair amount of knowledge in the process. Images portray before and after scenes in the shore station equipment room.
We'll have about a week to catch our breath, before launching into a rigorous two-week operational check of the Power Feed Equipment, followed by testing and commissioning of the Line Monitoring Equipment, both of which incorporate the submarine cables presently being laid in the ocean. A significant milestone indeed!
--Chris Hoyt, University of Washington OOI Field Operations Manager
*The Line Monitoring Equipment monitors the health of the fiber-optic lines and locates any cable faults.
**The Submarine Line Terminal Equipment consists of Transmission Terminal Equipment with multi-channel transmission capability for transmitting data to and from the undersea observatory nodes, the Line Monitoring Equipment, and an Element Management System that will be used to monitor optical line performance and amplifier status.
***The Power Feed Equipment powers all the undersea nodes and science-gathering devices, as well as the optical line amplifiers on the submarine fiber-optic cables.