- Visions18
- Visions17
- Visions16
- Visions15
- Visions14
-
Construction
- Node Installations Complete!
- Six on the Seafloor!
- New Segment 7
- Defining the SIA
- PN5A Successfully Deployed!
- PN 5A – Jointing Operations
- PN 5A Installation Continues
- On Site to Install PN5A
- Transit to Node 5A
- Port Call in Portland
- PN1D is Installed!
- Burial and Inspection Completed ...
- Humpbacks Visit
- Cable Burial Node PN1C
- Milestone: PN1C is Installed
- Photos of Final Inspection of P ...
- Another RSN Node is Born!
- Cable Burial Continues at Secon ...
- Second Node Installed!
- Splicing Node PN1B into Segment ...
- Recovering End of Segment 3
- Word for the Day: Persistence
- Major Milestone: First Node Ins ...
- Primary Node 1A Powered Up on D ...
- Recovering and Testing Cable Se ...
- OOI Primary Node Installation B ...
- Cable Installation Update
- Dolphins and Puffins and Molas, ...
- Day 51: Seabed Cable Lay Comple ...
- Dynamic Positioning
- Update on Cable Installation
- Completion of Segment 1 Burial
- Leaps and Bounds at the Shore S ...
- Segment 5 Installation Complete ...
- Laying Segment 5
- Bustling Shore Station
- At-Sea Installation Phases
- Installing the Land Cable
- TE SubCom Dependable Propulsion ...
- Divers at Work
- The Day After
- Second OOI Cable Landed
- Second Cable Landing Reschedule ...
- OOI Open House in Pacific City, ...
- The Cable has Landed!
- Last Grapnel Run Before Landing ...
- Preparing for the Cable Landing ...
- Seaplow 101
- Marine Mammal Observations
- Communicating with a Fishing Ve ...
- Cable Deployment Update
- Off Pacific City, Oregon
- Finished with First Segment
- Deploying Repeaters
- Start of First Cable Segment
- Leaving Astoria
- Meeting the Cable Ship in Astor ...
- Cable Laying Vessel Underway
- Photos of OOI Cable Loading
- Northern conduit installed
- Northern Conduit drilling compl ...
- Bubble test for the Southern Co ...
- Drilling of the Northern Condui ...
- Update on Drilling
July 2013
May 2013
December 2012
October 2012
August 2012
July 2012
April 2012
March 2012
January 2012
October 2011
September 2011
August 2011
July 2011
June 2011
March 2011
February 2011
October 2010
June 2010
May 2010
April 2010
- Visions13
- Visions12
- Visions11
- Enlighten
Meeting the Cable Ship in Astoria
Monday, June 27, 2011
Cecile Durand, the OOI Regional Scale Nodes Marine Maintenance Manager at the University of Washington, reports from Astoria, Oregon:
The TE SubCom Dependable has arrived in Astoria and is loading fuel and supplies for her two-month voyage to install the OOI/RSN cable. Representatives from Ocean Leadership, the University of Washington, the Oregon Fishermen’s Cable Committee (OFCC) and Protected Species Visual Observers (PSVOs) have joined the vessel and have been briefed on the details of the plan of work.
The installation team consists of TE Subcom personnel managed by their Engineer in Charge (EIC) and directed by L3 Maripro personnel (customer on board). The role of the UW and OL representatives on board will be to ensure that the OOI cable is laid according to the technical specifications. Two OFCC representatives are onboard to support the installation effort and verify that burial of the cable on the continental margin meets the RSN permit requirements. The primary role of the OFCC is to observe the installation operations and ensure that fishing hazards along the cable route are identified and recorded. The two PSVOs will monitor the presence of marine mammals or sea turtles entering the safety zone (500ft) along the cable route to ensure that no protected species is being endangered during the laying operations. In the afternoon we were informed that the departure will be delayed to the next day, June 28th, 18:00. The team is taking this extra time to settle down, install the equipment and prepare for departure.