Construction
- Node Installations Complete!
- Six on the Seafloor!
- New Segment 7
- Defining the SIA
- PN5A Successfully Deployed!
- PN 5A – Jointing Operations
- PN 5A Installation Continues
- On Site to Install PN5A
- Transit to Node 5A
- Port Call in Portland
- PN1D is Installed!
- Burial and Inspection Completed ...
- Humpbacks Visit
- Cable Burial Node PN1C
- Milestone: PN1C is Installed
- Photos of Final Inspection of P ...
- Another RSN Node is Born!
- Cable Burial Continues at Secon ...
- Second Node Installed!
- Splicing Node PN1B into Segment ...
- Recovering End of Segment 3
- Word for the Day: Persistence
- Major Milestone: First Node Ins ...
- Primary Node 1A Powered Up on D ...
- Recovering and Testing Cable Se ...
- OOI Primary Node Installation B ...
- Cable Installation Update
- Dolphins and Puffins and Molas, ...
- Day 51: Seabed Cable Lay Comple ...
- Dynamic Positioning
- Update on Cable Installation
- Completion of Segment 1 Burial
- Leaps and Bounds at the Shore S ...
- Segment 5 Installation Complete ...
- Laying Segment 5
- Bustling Shore Station
- At-Sea Installation Phases
- Installing the Land Cable
- TE SubCom Dependable Propulsion ...
- Divers at Work
- The Day After
- Second OOI Cable Landed
- Second Cable Landing Reschedule ...
- OOI Open House in Pacific City, ...
- The Cable has Landed!
- Last Grapnel Run Before Landing ...
- Preparing for the Cable Landing ...
- Seaplow 101
- Marine Mammal Observations
- Communicating with a Fishing Ve ...
- Cable Deployment Update
- Off Pacific City, Oregon
- Finished with First Segment
- Deploying Repeaters
- Start of First Cable Segment
- Leaving Astoria
- Meeting the Cable Ship in Astor ...
- Cable Laying Vessel Underway
- Photos of OOI Cable Loading
- Northern conduit installed
- Northern Conduit drilling compl ...
- Bubble test for the Southern Co ...
- Drilling of the Northern Condui ...
- Update on Drilling
July 2013
May 2013
December 2012
October 2012
August 2012
July 2012
April 2012
March 2012
January 2012
October 2011
September 2011
August 2011
July 2011
June 2011
March 2011
February 2011
October 2010
June 2010
May 2010
April 2010
- Visions13
- Visions12
- Visions11
- Enlighten
Today's photos and blog entry focus on Plow 101. The plow is 14.5 tons and capable of operating in water depths up to 1500m and 1.5m burial. The cable enters the plow thru the bellmouth, travels thru the plow and exits between the share and the depressor. The depressor ensures that the cable stays in the trench opened by the share. Plow speed is typically less than 0.5kts. There are three cables going from the ship to the plow.
1) The plow is rated for 40tons of bollard pull. The tow winch (center of photo at lower right) will render towing cable when tensions exceed 40 tons. Reducing ship's forward motion will also reduce tow tension.
2) The umbilical cable provides electro-optical connections to the plow to provide power and monitor/control plow equipment and provide live
video. The umbilical winch is on the starboard side in photo at lower right.
3) And, of course, the third is the telecom cable that is buried in the ocean floor, the OOI cable!
With three cables attached, launching and recovery of the plow is challenging. The plow will be lifted from the position in photo 1, moved to starboard over the cable trough and after the telecom cable is passed through the plow, the plow will be launched over the stern. There is a beacon on the plow that shows its exact position in relation to the cable ship. Combining this with the ship's GPS gives us a very precise geographical location of the cable. In the main photo at the top you also see the floats that will be used to float the telecom cable to the bore pipe during the shore landing.
--From Paul Hagstrom, Associate Project Manager/Senior Project Engineer (Regional Scale Nodes), Consortium for Ocean Leadership, onboard the TE SubCom Dependable.