- Visions18
- Visions17
- Visions16
- Visions15
- Visions14
-
Construction
- Node Installations Complete!
- Six on the Seafloor!
- New Segment 7
- Defining the SIA
- PN5A Successfully Deployed!
- PN 5A – Jointing Operations
- PN 5A Installation Continues
- On Site to Install PN5A
- Transit to Node 5A
- Port Call in Portland
- PN1D is Installed!
- Burial and Inspection Completed ...
- Humpbacks Visit
- Cable Burial Node PN1C
- Milestone: PN1C is Installed
- Photos of Final Inspection of P ...
- Another RSN Node is Born!
- Cable Burial Continues at Secon ...
- Second Node Installed!
- Splicing Node PN1B into Segment ...
- Recovering End of Segment 3
- Word for the Day: Persistence
- Major Milestone: First Node Ins ...
- Primary Node 1A Powered Up on D ...
- Recovering and Testing Cable Se ...
- OOI Primary Node Installation B ...
- Cable Installation Update
- Dolphins and Puffins and Molas, ...
- Day 51: Seabed Cable Lay Comple ...
- Dynamic Positioning
- Update on Cable Installation
- Completion of Segment 1 Burial
- Leaps and Bounds at the Shore S ...
- Segment 5 Installation Complete ...
- Laying Segment 5
- Bustling Shore Station
- At-Sea Installation Phases
- Installing the Land Cable
- TE SubCom Dependable Propulsion ...
- Divers at Work
- The Day After
- Second OOI Cable Landed
- Second Cable Landing Reschedule ...
- OOI Open House in Pacific City, ...
- The Cable has Landed!
- Last Grapnel Run Before Landing ...
- Preparing for the Cable Landing ...
- Seaplow 101
- Marine Mammal Observations
- Communicating with a Fishing Ve ...
- Cable Deployment Update
- Off Pacific City, Oregon
- Finished with First Segment
- Deploying Repeaters
- Start of First Cable Segment
- Leaving Astoria
- Meeting the Cable Ship in Astor ...
- Cable Laying Vessel Underway
- Photos of OOI Cable Loading
- Northern conduit installed
- Northern Conduit drilling compl ...
- Bubble test for the Southern Co ...
- Drilling of the Northern Condui ...
- Update on Drilling
July 2013
May 2013
December 2012
October 2012
August 2012
July 2012
April 2012
March 2012
January 2012
October 2011
September 2011
August 2011
July 2011
June 2011
March 2011
February 2011
October 2010
June 2010
May 2010
April 2010
- Visions13
- Visions12
- Visions11
- Enlighten
Brian Ittig, OOI RSN Marine Operations Manager at the University of Washington, boarded the TE SubCom Dependable in Portland, Oregon, last Friday as Cecile Durand, OOI RSN Marine Maintenance Manager at the University of Washington, disembarked after Phase I of the Primary Node Installation work. Brian reports on work accomplished since the Dependable departed Portland on Friday, August 3:
After OOI RSN Primary Nodes 3A and 3B were loaded, positioned on the aft deck, and successfully tested, the vessel departed Portland and transitted to the Primary Node 5A deployment site in the middle of the Juan de Fuca tectonic plate. Segment 6 grapnel operations began as soon as the vessel arrived on site at 1200h PDT, Saturday, 4 August. The first task was to recover the end of cable Segment 6. Initial grapnel operations were successful and the ground rope was engaged in the second hook, or "jammer," in the grapnel. Approximately 6 km of cable Segment 6 were recovered, repositioned to the North, and "buoyed off" at 1330h PDT Sunday, August 5. This deployment of the cable end to the buoy will assist in future operations when it is time to bring the cable ends onboard the ship and join them to the node.
Next step was to transit to the Segment 5 cable grounds where grapnel operations began at 1500 h PDT. The Segment 5 ground rope was successfully engaged and the cable was brought onboard early in the morning of Monday, August 6. Approximately 12 km of cable Segment 5 have been recovered and are currently being re-positioned to the final cable route.
A bit of background on Primary Node 5A
The Primary Node 5A deployment site is in approximately 2850 m water depth. PN5A will be the first of three primary nodes deployed on the northern line of the OOI RSN cabled infrastructure. This northern section, which runs out to Axial Seamount, is comprised of approximately 530 km of cable.
The configuration of Primary Node 5A differs from the other primary nodes to be installed along the northern line: PN5A will be attached to three submarine cables, whereas the other nodes will be attached to two (PN3B) or one (PN3A). The additional, third, cable is a stub that will support potential future expansion of the cabled infrastructure and will enable adding more primary nodes without having to recover PN5A. Due to several factors, including installation configuration and water depth, the deployment of Primary Node 5A is expected to take seven days.
--Brian Ittig, OOI RSN Marine Operations Manager, University of Washington, onboard the TE SubCom Dependable
Transit to Node 5A
Saturday, August 04, 2012
According to Paul Hagstrom, the ship left the dock in Portland, Oregon, at 1300h PDT on Friday, August 3, and was crossing the Columbia River Bar at Astoria some 8 hours later. ...
OOI Primary Node Installatio
Wednesday, July 11, 2012
Our very first operation has been a success! We recovered the end of cable Segment 1 using a grapnel towed behind the vessel. ...
Mid Plate PN5A
The Mid-Plate Primary Node, located between Axial Seamount and the Pacific City Shore Station, is important because it provides one of the few mid-p ...