- Visions18
- Visions17
- Visions16
- Visions15
- Visions14
-
Construction
- Node Installations Complete!
- Six on the Seafloor!
- New Segment 7
- Defining the SIA
- PN5A Successfully Deployed!
- PN 5A – Jointing Operations
- PN 5A Installation Continues
- On Site to Install PN5A
- Transit to Node 5A
- Port Call in Portland
- PN1D is Installed!
- Burial and Inspection Completed ...
- Humpbacks Visit
- Cable Burial Node PN1C
- Milestone: PN1C is Installed
- Photos of Final Inspection of P ...
- Another RSN Node is Born!
- Cable Burial Continues at Secon ...
- Second Node Installed!
- Splicing Node PN1B into Segment ...
- Recovering End of Segment 3
- Word for the Day: Persistence
- Major Milestone: First Node Ins ...
- Primary Node 1A Powered Up on D ...
- Recovering and Testing Cable Se ...
- OOI Primary Node Installation B ...
- Cable Installation Update
- Dolphins and Puffins and Molas, ...
- Day 51: Seabed Cable Lay Comple ...
- Dynamic Positioning
- Update on Cable Installation
- Completion of Segment 1 Burial
- Leaps and Bounds at the Shore S ...
- Segment 5 Installation Complete ...
- Laying Segment 5
- Bustling Shore Station
- At-Sea Installation Phases
- Installing the Land Cable
- TE SubCom Dependable Propulsion ...
- Divers at Work
- The Day After
- Second OOI Cable Landed
- Second Cable Landing Reschedule ...
- OOI Open House in Pacific City, ...
- The Cable has Landed!
- Last Grapnel Run Before Landing ...
- Preparing for the Cable Landing ...
- Seaplow 101
- Marine Mammal Observations
- Communicating with a Fishing Ve ...
- Cable Deployment Update
- Off Pacific City, Oregon
- Finished with First Segment
- Deploying Repeaters
- Start of First Cable Segment
- Leaving Astoria
- Meeting the Cable Ship in Astor ...
- Cable Laying Vessel Underway
- Photos of OOI Cable Loading
- Northern conduit installed
- Northern Conduit drilling compl ...
- Bubble test for the Southern Co ...
- Drilling of the Northern Condui ...
- Update on Drilling
July 2013
May 2013
December 2012
October 2012
August 2012
July 2012
April 2012
March 2012
January 2012
October 2011
September 2011
August 2011
July 2011
June 2011
March 2011
February 2011
October 2010
June 2010
May 2010
April 2010
- Visions13
- Visions12
- Visions11
- Enlighten
Steady progress continues to be made on the installation of the northern section of the OOI RSN cabled infrastructure to Axial Seamount.
The end of cable segment 6 was successfully retrieved by grapnel operations and approximately 10.2km of segment 6 was recovered and repositioned along the final cable route. The end of cable segment 6 was deployed to a buoy,
Operations have also included recovering 27.1 km of cable segment 7, which was installed in summer 2011. A post-installation ROV survey revealed that part of this cable segment had been laid through a new and active hydrothermal vent field on the flank of Axial volcano. Because of the potential for cable damage from the extremely high temperatures in this vent field, the decision was made to recover the 2011-laid cable and install a new segment 7 as part of the primary node installation operations now underway. The TE SubCom Dependable, the vessel being used to install the primary nodes, is also the commercial vessel that was used to lay the primary cable segments in summer 2011.
Segment 7 connects Primary Nodes 3A and 3B and is being installed towards Primary Node 3A, from west to east. As of 0300h PDT, we have completed approximately 50% of the new cable installation along a route that avoids the active hydrothermal vent field.
Upon completion of the cable segment 7 installation, the segment 6 buoy will be recovered and Primary Node 3A will be spliced into the system.
For video taken at Axial Volcano during the VISIONS '11 cruise in August 2011, visit the expedition website here.
-- Brian Ittig, OOI RSN Marine Operations Manager, University of Washington, onboard the TE SubCom Dependable